Bus Connects - Transforming City Bus Services

Greenhills to City Centre - Core Bus Corridor

Emerging Preferred Route Public Consultation January 2019

Contents - Page 1

Introduction - (Section 1) Page 2

1.1 Background

In June 2018 the National Transport Authority (NTA) published the Core Bus Corridors Project Report. The report was a discussion document outlining proposals for the delivery of a core bus corridor network across Dublin. It set out the vision for the provision of 230kms of dedicated bus lanes and 200km of cycle lanes/tracks on sixteen key bus corridors.

Separately in July 2018 the Dublin Area Bus Network Redesign, which is the redesign of bus services, started its first public consultation phase. Around 30,000 submissions including signed petitions and online survey responses were received by the end of September. Over the coming months all of these submissions will be reviewed and assessed. Following that process a revised network design will be published during 2019 for a second public consultation. It is envisaged that the implementation of the final network will take place in 2020. The network redesign can be implemented on the existing road network with some enhancements at key interchange locations.

The public consultation for the sixteen radial core bus corridors will now take place on a phased basis from November 2018 until May 2019. Each phase will be for a set number of corridors to be consulted on over a period of months. These public consultations phases will be the start of a detailed process of engagement and communication. All of which will take place prior to detailed designs being finalised and planning permissions sought.

This document is one of a series of sixteen, each dedicated to a single core bus corridor. The document provides a written description of the emerging preferred route from start to finish with supporting route maps. It explains the step by step process for engagement and consultation for potentially impacted property owners and the general public. It also outlines the process for planning and construction of the core bus corridor network including expected timelines.

1.2 Why does Dublin need a core bus corridor network? - Page 3

Congestion

Congestion is one of the most significant challenges facing the Dublin region and needs to be addressed to safeguard the growth of the Dublin region and keep people moving. Ireland's economic recovery from the recession is seeing significant increases in the number of people working and travelling across Dublin. The number of commercial vehicles continues to rise as does the number of tourists. The commuter areas surrounding Dublin continue to spread and grow in a low density manner. Growth areas can only be served in the short and medium term by the bus as opposed to long-term projects such as rail and Luas.

At present bus lanes are in place for less than one third of a bus journey on the busy corridors. This means buses are competing for space with general traffic and so are affected by the increasing levels of congestion.

Growing Population

It is predicted that the population for the Dublin region will grow 25% by 2040, bringing it to almost 1.5m for the region. This huge growth in population has to be accommodated with a quality public transport system.

The bus system can deliver

We need to invest in the bus system because the bus system is the main component to meet our future transport needs. A good bus system has the reach and flexibility to service all the new housing developments, business parks, hospitals, colleges and retail shops across Dublin. It is a proven solution and is the main form of public transport across Dublin with 67% of public transport journeys each day made by bus. The bus system carries three and four times the number of people who travel on Luas or Dart and commuter rail.

1.2 Why does Dublin need a core bus corridor network? - Page 4

People want to cycle

The core bus corridor project is not just about the provision of bus lanes. Under this project we will also deliver 200km of segregated cycling infrastructure to make cycling safer and more attractive than ever before. This initiative is the foundation of the overall cycle network for the Greater Dublin Area.

Commuting to work by bicycle has increased by 43% since 2011. Again this growth represents a clear choice that people are making to cycle. This project will support that trend and is a vital component of creating a sustainable transport system for people across Dublin. Safe cycling facilities across the 16 key bus corridors will provide people, families and their children a suitable environment to cycle where they want and when they want.

People want to use public transport

The need to build a core bus network is being driven by increases in congestion and also by the significant shift of people choosing to use public transport. People want to use it and should have a reliable and efficient bus system to travel on. Based on 2017 canal cordon figures over 70% of people travelling into the city each morning do so by sustainable transport modes and mostly by bus. Cars only account for 30% of travel into the city centre each day and therefore the amount of road space allocated to sustainable transport needs to reflect that position.

1.3 What is BusConnects Dublin? - Page 5

BusConnects Dublin is a major investment programme to improve public transport in Dublin.

It aims to overhaul the current bus system in the Dublin through a 10 year programme of integrated actions to deliver a more efficient, reliable and better bus system for more people.

1.4 What are the benefits of this project? - Page 6

Journey Time Savings

The core bus corridor project will deliver journey time savings of up to 40-50% on each corridor. Dedicated bus lanes can significantly increase bus travel speeds and reliability. Improved journey times and reducing the amount of time people spend commuting will make bus travel more attractive and reduce our reliance on car travel. The more convenient the bus system is, the faster the modal shift will be for people from the car to the bus. Not only will current bus users and cyclists benefit but future commuters will be able to avail of a better system as the improved bus and cycle lanes are built.

Accessibility for all

Accessibility is about people's ability to reach the destinations and services they want to get to. This means both people's level of mobility and the costs of travelling. There are many tens of thousands of people across Dublin who cannot drive a car, do not have a car and are completely reliant on the bus service. The bus lane improvements will enhance accessibility for the elderly and mobility impaired because all buses are accessible and bus stops, bus shelters and footpaths will support easy boarding and disembarking of the buses.

Better cycling facilities

This project will see the provision of much needed cycling facilities around the city region. Across the 16 radial bus corridors there will be over 200kms of high quality cycling facilities provided. These new or improved cycle lanes will be segregated from bus lanes and general traffic where feasible.

1.4 What are the benefits of this project? - Page 7

Pedestrians and Local Urban Centres

In addition to bus lanes and cycling facilities this project is an opportunity to enhance and improve local areas. This project is focused on making things better for commuters and communities around the bus corridors. Along each route, improvements and enhancements will be made to footpaths, walkways and pedestrian crossings. Funding and investment for local urban centres with additional landscaping and outdoor amenities will be provided.

Building a sustainable city and addressing climate change

By providing a better bus system for Dublin we can make it a more attractive place to live, work and visit. A good public transport system is vital to support the economic activity of any city and can also address the need to improve air quality and reduce CO2 emissions. Tackling the challenges of climate change is a priority for the Government and moving more people to public transport is a key component of the solution.

1.5 What does the core bus corridor project entail? - Page 8

The core bus corridor project proposes the provision of 230 kilometres of bus lanes on sixteen of the busiest bus corridors and 200 kilometres of cycle lanes and tracks as published in the discussion document, Core Bus Corridor Project Report June 2018.

The layout below shows the arrangement that we are seeking to achieve on each corridor. However, this optimal layout is difficult to achieve in practice and we have proposed alternative solutions in various places to deliver the required bus and cycling lanes.

Bus lanes are needed to make the current and future bus system operate efficiently, reliably and punctually. Our intention is to develop these bus corridors so that each will have continuous bus priority - in other words, a continuous bus lane in each direction as well as maintaining two general traffic lanes. In addition we also want to provide safe cycling facilities, segregated where possible from other vehicular traffic. This will remove the delays currently experienced which will grow worse as congestion increases.

Radial Core Bus Corridors Emerging Preferred Routes - Page 9

  1. Clongriffen to City Centre
  2. Swords to City Centre
  3. Ballymun to City Centre
  4. Finglas to Phibsborough
  5. Blanchardstown to City Centre
  6. Lucan to City Centre
  7. Liffey Valley to City Centre
  8. Clondalkin to Drimnagh
  9. Greenhills to City Centre
  10. Tallaght to Terenure
  11. Kimmage to City Centre
  12. Rathfarnham to City Centre
  13. Bray to City Centre
  14. UCD Ballsbridge to City Centre
  15. Blackrock to Merrion
  16. Ringsend to City Centre

Emerging Preferred Route - (Section 2)Page 10

2.1 The Emerging Preferred Route for Greenhills to City Centre

The Emerging Preferred Route set out in this consultation document was identified following an assessment of various alternatives.

The route selection process involved identification and consideration of possible options taking account of criterias including local impacts on property frontage, existing traffic patterns and broad assessment of environmental impacts. A Feasibility Report setting out details of the assessment work undertaken is available on www.busconnects.ie.

Arising from that work an Emerging Preferred Route has been identified for this corridor and public feedback on that proposal is now sought. It is important to know that this option is not adopted yet. Only following this consultation and review of the submissions received will a decision on the final Preferred Route be made.

2.2 Greenhills to City Centre Overview

The Greenhills Core Bus Corridor (CBC) commences on Belgard Square West at the junction with Cookstown Way. From here the CBC is routed along Belgard Square West and Belgard Square North as far as the junction with Belgard Road. At this point the CBC enters the Institute of Technology Tallaght campus and follows the existing internal road through the campus, exiting at the existing junction on Greenhills Road. From here the CBC is routed along the R819 Greenhills Road, Ballymount Avenue, Calmount Road, and Walkinstown Road as far as the junction with the R110 Long Mile Road.

It is proposed to realign the existing Greenhills Road in two locations on this section: along an existing road reservation between Parkview and Treepark Road, and through Ballymount Industrial Estate by way of extending both Ballymount Avenue and Calmount Avenue to connect to Greenhills Road at new signalised junctions.

From the junction of the R110 Long Mile Road and the R819 Walkinstown Road the CBC is routed along the R110 Drimnagh Road, Crumlin Road, Dolphin's Barn, Cork Street, St. Luke's Avenue, The Coombe, and Dean Street to the junction with the R137 Patrick Street. The CBC is then routed along Patrick Street and Nicholas Street to the junction with Christchurch Place where it will join the prevailing traffic management regime in the city centre.

2.2.1 Belgard Square South to Greenhills Road - Belgard Square West, Belgard Square North, Institute of Technology Tallaght Access Road

The Greenhills CBC commences at the existing roundabout junction on Belgard Square South. It is proposed to change the roundabout to a fully signalised junction with improved pedestrian facilities. Belgard Square West is intended to be a bus only route not accessible to general traffic. Between Belgard Square South and Tallaght Cross West / Broadfield Hall access to and from these buildings and neighbouring developments will still be permitted from Belgard Square West. Bus traffic across Old Blessington Road will be controlled by a bus gate traffic light system. Access to and from the Old Blessington Road to Belgard Square West will be permitted.

It is proposed to change the roundabout junction on Belgard Square North at the Tallaght Hospital Entrance and Cookstown Way to a fully signalised junction to accommodate new bus lane and pedestrian facilities. The roundabout junctions at Belgard Square East and at Belgard Road will also be replaced with new signalised junction arrangements. From Belgard Road it is proposed to route the bus corridor through the grounds of the Institute of Technology Tallaght (ITT). It is intended to change one of the inbound lanes on the entry road to a contra-flow bus lane. It proposed to provide new bus stop facilities within the campus.

The ITT junction with the Greenhills Road is currently an uncontrolled priority junction. It is proposed to upgrade this junction to a fully signalised junction with pedestrian crossing facilities.

2.2.2 Greenhills Road to Walkinstown Roundabout - Greenhills Road, Ballymount Avenue, Calmount Road, back to rejoin Greenhills Road Page 11

Between the ITT access junction and the junction with Mayberry Road along the Greenhills Road it is intended to provide one bus lane, one traffic lane and a cycle track in both directions. To accommodate the road cross section it is proposed to utilise limited land take along this section on the west side of the existing Greenhills Road with some limited short sections of land take likely also on the east side.

To improve the operation of the existing junction and minimise landtake, it is proposed to introduce a right turn ban from Greenhills Road to the entrance to Harvey Norman store and right turn ban from the Greenhills Road to Hibernian Industrial Estate. Access from Harvey Norman to Greenhills Road will be maintained at the junction. Right turning vehicles for Harvey Norman will be directed to the Airton Road junction. At this junction, vehicles will be able to turn right and access the Harvey Norman store from this road.

Right turning vehicles for the Hibernian Industrial estate will be directed to the next junction (at Agnelli Motor Park) where full access will be maintained.

Between Mayberry Road and Tymon Lane it is proposed to undertake major changes to the local road network. South Dublin County Council has identified this section of Greenhills Road for upgrade under their current County Development Plan. It is intended to implement some of these road construction works as part of this scheme. The existing Greenhills Road will be retained as an access road for Park View Estate. A new Greenhills Road will be constructed on the green space south of Birchview Avenue and Treepark Road. Traffic to the Old Greenhills Road will be restricted to local traffic only and movement bans will be proposed to enforce this. This new section of road will be wide enough to accommodate one bus lane, one traffic lane and a cycle track in both directions with new bus stop and pedestrian crossing facilities.

The existing M50 bridge crossing will be retained; however it will present a width restriction. This crossing may be reviewed in the next design stage. It is currently proposed to maintain one lane of general traffic in each direction. However, bus priority will be achieved through a queue relocation facility on the approaches to the bridge crossing. After the bridge crossing, it is proposed to widen the road again to accommodate one bus lane, one traffic lane and a cycle track in both directions.

At Keadeen Park it is proposed to close Greenhills Road to traffic. Traffic will be directed on to a new road link connecting the road to Ballymount Avenue. The new road will tie back into the existing road networks at Calmount Road. The junction between Ballymount Avenue and Calmount Road will be upgraded from a roundabout to a signalised junction with improved pedestrian facilities. The bus route will be directed down Calmount Road. The existing road is intended to be widened to incorporate bus and cycle lanes. It is proposed to connect Calmount Road to Greenhills Road with a new link road. It also is proposed to connect the existing Greenhills Road to Calmount Road with a new link road through Calmount Avenue. Some limited land take will be required to construct a new roundabout at this proposed junction.

Between the Calmount Road and Walkinstown Roundabout, it is proposed to maintain one bus lane, one traffic lane and a cycle track in both directions. This will require limited land take on the south side of Greenhills Road. Some current access arrangements along this section of road will need to be reviewed. It is intended to upgrade the existing roundabout junction to incorporate improved pedestrian and cyclist facilities. The indicative extents of this land take are included in the Appendix of this brochure.

2.2.3 Walkinstown Roundabout to Dolphin Road - Walkinstown Road, Drimnagh Road, Crumlin Road Page 12

On Walkinstown Road between Walkinstown Roundabout and the Long Mile Road, it is proposed to provide one bus lane and one general traffic lane in both directions. There is insufficient space to accommodate dedicated cycle lanes on this section of road. To accommodate this cross section, it is proposed to utilise land take to west of the Walkinstown Road between Walkinstown Avenue and Kilnamanagh Road. Land take to the east of Walkinstown Road may be required between Kilnamanagh Road and Long Mile Road. It is proposed to introduce a right turn ban from Walkinstown Road to Kilnamanagh Road. Kilnamanagh Road will remain accessible from Walkinstown Road through Walkinstown Drive. It is also intended to introduce a right turn ban for right turning traffic from Walkinstown Road to the southern entrance of the SuperValu supermarket.

To accommodate cyclists on this section of the route, an alternative cycle route is proposed along Bunting Road and St. Marys Road providing a quiet route linking Walkinstown Roundabout with Kildare Road.

It is proposed to upgrade the existing Long Mile Road / Walkinstown Road junction to provide bus priority signal facilities and improved pedestrian crossing. On Drimnagh Road it is proposed to maintain one bus lane, one general traffic lane and one cycle track in both directions. To allow this revised cross section some limited land take from property between Balfe Road and Kildare Road may be required.

On Crumlin Road between Kildare Road and Sundrive Road it is intended to restrict the proposed road cross section to one bus lane and one general traffic lane. Due to width restrictions in the area there is insufficient space to provide dedicated cycle lanes. To accommodate this restricted cross section it will be necessary to acquire land along Crumlin Road. The indicative extents of this land take are included in the Appendix of this brochure. Additional bus stops will be provided along this route.

To facilitate cyclists, it is proposed to redirect them through Kildare Road. To improve local safety it is intended to introduce a no entry sign at the junction of Kildare Road and Clonard Road for traffic in both directions. This would prevent general through traffic; however buses, taxis and cyclists movements will remain unrestricted along Kildare Road. Eastbound traffic would be directed along Clonard Road, through Downpatrick Road on to Bangor Road. Westbound traffic would also be directed up Clonard Road onto the Crumlin Road. Cyclists would proceed from Kildare Road to Clogher Road and be redirected along Slane Road. From Slane Road, cyclists would travel along Downpatrick Road and on Sundrive Road. On Sundrive Road, a new cycle lane in both directions is to be provided between the junction of Downpatrick Road and Crumlin Road.

At the junction between Crumlin Road and Herberton Road, it is proposed to modify the existing layout to improve the kerb alignments and provide improved pedestrian crossing facilities. On the Crumlin Road between Herberton Road and Dolphin Road it is proposed to maintain one bus lane and one general traffic lane in both directions. There is insufficient road width on this section to provide dedicated cycle tracks.

2.2.4 Dolphin Road to Christchurch Place - Dolphins Barn, Cork Street, St Luke's Avenue, Dean Street, Patrick Street, Nicholas Street, Christchurch Place Page 13

Between Dolphin Road and South Circular Road, it is intended to provide one bus lane, one general traffic lane and one cycle track in both directions. To improve bus priority at the South Circular Road junction, it is proposed to introduce a left turn ban in both directions. To make this turning movement drivers will be directed down Rueben Road and onto Haroldville Avenue or onto Parnell / Dolphin Road.

Between South Circular Road and Ardee Street and on along Dean Street it is proposed to have one bus lane, one general traffic lane and one cycle track in both directions. It is also intended to upgrade the Ardee Street junction with improved pedestrian facilities.

It is proposed to modify the Kevin Street / Dean Street junction to facilitate improved cycle way facilities. There is currently insufficient road width on Dean Street to facilitate bus lanes but bus priority from St. Luke's Avenue will be maintained with a new Bus Only signal.

Between Dean Street Junction and Christchurch Place it is proposed to have one bus lane, one general traffic lane and one cycle track in both directions. The cross section would be accommodated by removing the central median and realigning the existing kerb line. Some on-street loading bays will be maintained between Bride Road and Bull Alley Street. On Christchurch Place the route will join the prevailing traffic management regime in the city centre.

2.3 Key Facts

Challenges and Mitigations - (Section 3) Page 14

3.1 The Challenges

It's important to acknowledge that the choices required to deliver this step-change in the performance of the bus system will be difficult. However, the decision-making needs to be done now and not postponed until the problem is far greater. Some of the decisions may be hard but they are being made because we believe that these plans have the potential to fundamentally transform the way public transport works in Dublin.

Our challenge now is to respond to the needs of a modern city by providing a fit-for-purpose bus system, built on a streetscape that dates back centuries. Needless to say the streets were not designed to move the number of people that now need to travel in and out of the city each day. Some of the city's inner suburbs date back to Victorian times, with road layouts suited to more modest levels of traffic than we see today.

Not all the impacts will be felt equally and some locations will require more changes than others. Over the years those modifications that were easier to implement - the ones that caused little or no disruption - have been made. This means that there are no longer any simple changes which we can make that would generate meaningful benefits.

If we don't decide to make these changes now, then we need to accept that Dublin will become increasingly congested and a less attractive place to live and work, both for us now and for future generations.

3.2 Potential Impacts

3.2.1 Traffic changes

By creating more priority for buses and cycling there will be changes to how traffic currently moves around the streets. On some corridors, certain roads may become one-way, new bus-only sections will be introduced and in some places general traffic will have to take new routes in and out of the city. Additional cycle routes will be built, generally segregated from vehicular traffic, and pedestrian crossings will be added and moved in some areas.

3.2.2 Land take

Because there is so little unused space along these busy roads, it will often not be possible to accommodate the bus lanes and cycle lanes in the width available. In order to achieve the required space it will be necessary, in places, to acquire parts of front gardens, driveways and land in front of commercial properties to allow the bus and cycle lanes to be provided. This would require rebuilding new garden walls and driveways a short distance back from the existing road boundary.

3.2.3 Reduction of On-Street Parking and Loading Facilities

Because the roads that need widening travel through residential and business areas there will be a need to reduce the amount of on-street parking and loading facilities to accommodate the new layout.

3.2.4 Removal of Trees - Page 15

As with the need to remove some parts of front gardens and footpaths there will be also be a need to remove trees along some of the corridors.

3.2.5 Road Works and Construction Sites

Widening roads, and building bus and cycle lanes, requires construction work. There will be excavation of the existing roads, plus parts of gardens and footpaths where needed. There will be resurfacing, kerbing, replanting and landscaping. As with any work site and road works, there will be a certain level of noise, dust and temporary traffic diversions.

3.3 How we will address those challenges - Page 16

Obviously these challenges and impacts are significant. Every feasible option is being looked at to minimise the disruption to people, their property and the wider local community. Where there is simply no viable alternative, and where we know we have to remove trees, portions of gardens, driveways or parking, we will ensure appropriate mitigation measures are put in place, wherever practicable.

As part of this public consultation potentially impacted property owners will be contacted directly by the NTA and a direct dialogue will commence. As each individual property owner will have specific and personal issues there will be a dedicated liaison team to engage with this group on an individual basis.

There are principles for mitigation, statutory compensation and reparation which will be adhered to by the NTA as part of the statutory planning process. However, below are some of the measures that we envisage will be included. This list is not exhaustive and we anticipate that there will be other measures that will need to be put in place.

3.3.1 Traffic Changes

Where general traffic is diverted and re-routed, adequate signage and road markings will be provided for people to find their way. Measures will be implemented to ensure that "rat-runs" do not emerge as a consequence of the re-routed traffic. Also, local access will be maintained where new bus-only sections or one-way systems are brought in for residents and commercial properties.

3.3.2 Land take

Where lands, such as parts of gardens and driveways, are being acquired for widening we will purchase the portion of front gardens and driveways from property owners; ensure new landscaping and replanting of the gardens, reinstatement of driveways as well as providing compensation for the garden and driveway portion loss and disruption.

Where private and public walls or fencing are removed we will rebuild new garden walls and replace fencing where gardens have been affected and shortened. Also, where public or commercial walls and fencing have been taken they will be rebuilt and replaced.

3.3.3 On street parking and Loading Facilities - Page 17

Where there is a loss of on-street parking and loading facilities we will seek to provide, where feasible, alternative arrangements close by for residents and businesses.

3.3.4 Trees

Where trees are removed from roadsides and footpaths we will put in place a comprehensive replanting programme. This programme will use mature or semi-mature ready-grown trees where appropriate and, where it is feasible, plant them as close as possible to the original locations.

3.3.5 Urban Centre Improvements

We will look for areas along the busy corridors where it is possible to improve the existing local spaces and the existing landscaping. It is important to use this opportunity to not only replace what is removed but to enhance the local areas. To do so, we will consult with the local authorities on such urban centre improvements and collectively seek to create attractive local environments.

3.3.6 Road Works and Construction Sites

During the construction stages the construction sites will be localised and managed on a road by road basis. The size of each work site and the hours of working will have to take into consideration the residential nature of many of the roads. Traffic management will be very important to keep the traffic moving and ensuring local access for people and deliveries is always maintained.

The Process for the Acquisition of Land - (Section 4) Page 18

Where the potential for impacts on private lands have been identified, the following process applies:

Q4 2018 - Q2 2019 NTA will issue information letters (not formal compulsory purchase order (CPO) notifications) to potentially impacted land owners and/or occupiers along each Core Bus Corridor. Potentially impacted includes for example, the acquisition of parts of front gardens, walls, fences, gates, driveways and the rebuilding of same to make way for street widening. The intention of this is to start a direct dialogue between NTA and the potentially impacted parties.

During 2019 to prepare the statutory planning documentation, the project design and environmental impact assessment will be progressed. During this time NTA will endeavour to minimise impacts on private lands. Direct dialogue between NTA and potentially impacted parties will continue to understand the likely impact of the proposed development and what arrangements can be made to minimise and where possible avoid those impacts.

End of 2019 / start of 2020 NTA will finalise the statutory planning documentation and will serve formal notice on the actual impacted owners of land proposed to be compulsorily purchased for the project. It will make a formal application to An Bord Pleanála for confirmation to compulsorily purchase necessary lands for purposes of constructing upgraded bus-lanes and bike-lanes.

During 2020 An Bord Pleanála will consider the planning application. There will be a period of statutory public consultation to allow those notified as being subject to CPO, and the public at large, to make submissions and/or objections to An Bord Pleanála. This will be followed by an Oral Hearing by An Bord Pleanála if deemed necessary. The statutory process will conclude with a decision by An Bord Pleanála on whether to:

  1. Approve the application, approve with conditions, or refuse the application; and
  2. Confirm, amend, or reject the CPO.

From 2021 onwards if An Bord Pleanála grants approval NTA will commence valuations and negotiations to acquire the lands in the CPO, and progress construction of the project. The construction of each core bus corridor will take up to two years to complete. The construction start dates for each of the 16 corridors will be managed over the period 2021 through 2027.

4.1 How the project will progress - how and when to get involved - Page 20

4.1 How the project will progress - how and when to get involved (continued) - Page 21

In 2021 to 2027 Acquisition Overview:

Constuction commences on a phased basis - each corridor upgrade will take up to 2 years to complete

Start of property acquisition and construction

How to take part in the public consultation - (Section 5) Page 22

Please remember that the plans that we are publishing are proposals and that no final decision has been made on these matters in advance of the public consultation. We welcome all of your views.

Where you do not like a proposal, please consider suggesting an alternative solution or other option for consideration. But do bear in mind that bus transport is, and will continue to be, the main form of public transport for most areas of the Dublin region and an alternative of providing an underground rail system is simply not a viable option for most parts of Dublin.

5.1 Potential impacted lands

If your property is potentially impacted by the proposals, a letter will have been hand delivered to the property and details of how to engage with the NTA are detailed in that letter. A dedicated property liaison representative will be available to meet with individual property owners and provide regular updates on the project.

5.2 General queries

The project website www.busconnects.ie has a dedicated section for the Core Bus Corridor project. Users can access the site to find out more about the project and download copies of the key studies that have been carried out.

General queries can be directed to a dedicated Freephone - 1800 303 653 or by email to cbc@busconnects.ie

5.3 How to engage

We are inviting submissions in relation to the proposals set out in this Public Consultation Document.

Written submissions and observations may be made by:

Online:

Through the online form in the "Public Consultation" section of the Core Bus Corridor page on our website: www.busconnects.ie

Or by email to:

cbc@busconnects.ie

Or by post to:

Core Bus Corridor Project

National Transport Authority Dún Scéine Harcourt Lane Dublin 2 D02 WT20

Appendices - Index and Route Maps - (Section 6) Page 24

Greenhills to City Centre - Page 25&47;26

NOTE: The following are descriptions of maps by Ordnance Survey Ireland - Government of Ireland. All rights reserved. Licence Number EN 0082118 National Transport Authority.

Index Map of Greenhills to City Centre including nodes from Tallagh, Ballymount, Greenhills, Drimnagh, Crumlin, Rialto, Dolphins Barn, The Liberties to Christchurch.

Map 1 Emerging Preferred Route - Page 27

Cookstown Way,Belgard Square West &South at junction EXISTING ROUNDABOUT TO BE CONVERTED TO FULLY SIGNALISED JUNCTION WITH PEDESTRIAN FACILITIES, NO LEFT TURN SIGN (RUS 013) before Belgard Square West, NO Right TURN SIGN (RUS 012) before Belgard Square West (Except Buses) and PROPOSED RAISED TABLE at Belgard Square West.

Map 2 Emerging Preferred Route - Page 28

Belgard Square West to Old Blessington Road PARKING PERMITTED (RUS 018) NO LEFT TURN SIGN (RUS 013), and NO Right TURN SIGN (RUS 012) except buses on both roads.New Indented Bus Bays on Belgard Square West.

Map 3 Emerging Preferred Route - Page 29

Belgard Square West, EXISTING ROUNDABOUT TO BE CONVERTED TO FULLY SIGNALISED JUNCTION WITH PEDESTRIAN FACILITIES with Bus Only signal.

Map 4 Emerging Preferred Route - Page 30

Belgard Square Nortt to Belgard Road, ITT, NO Right TURN SIGN (RUS 012), PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) at Belgard Square and Belgard Road, EXISTING TRAFFIC LANE CONVERTED TO CONTRA-FLOW BUS LANE at ITT Access Road.

Map 5 Emerging Preferred Route - Page 31

ITT, EXISTING TRAFFIC LANE CONVERTED TO CONTRA-FLOW BUS LANE, PARKING BAYS AS PER EXISTING LAYOUTat Willow Road to Westland Park.

Map 6 Emerging Preferred Route - Page 32

ITT Access Road onto Greenhills Road PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), EXISTING I.T. ENTRANCE TO BE CONVERTED TO FULLY SIGNALISED JUNCTION WITH PEDESTRIAN FACILITIES, EXISTING BRIDGE STRUCTURE TO BE MODIFIED.

Map 7 Emerging Preferred Route - Page 33

Greenhills Road to Hibernian Industrial Estate At Arton RoadPROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), EXISTING JUNCTION TO BE UPGRADED TO PROVIDE BUS PRIORITY FULLY SIGNALISED WITH PEDESTRIAN FACILITIES, POTENTIAL UPGRADE TO TRAFFIC SIGNALS TO FACILITATE ACCESS TO PROPOSED DEVELOPMENT ON EASTERN SIDE OF GREENHILLS ROAD at Hibernian Industrial Estate.

Map 8 & Map 8 Emerging Preferred Route - Page 34

Greenhills Road to Mayberry Road PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), EXISTING JUNCTION TO BE UPGRADED TO PROVIDE BUS PRIORITY FULLY SIGNALISED WITH PEDESTRIAN FACILITIES at Mayberry Road.

Map 9 Emerging Preferred Route - Page 35

Greenhills Road to Castletymon Road showing LOCAL REALIGNMENT OF GREENHILLS ROAD THROUGH OPEN SPACE with NO LEFT TURN SIGN (RUS 013), and EXISTING SIGNALISED JUNCTION CONVERTED TO PRIORITY CONTROLLED JUNCTION at Castletymon Road. NEW VEHICLE TURNING AREA at Old Greenhills Road.

Map 10 Emerging Preferred Route - Page 36

Greenhills Road, Treepark Road to Tymon Lane New Toucan Crossing at Treepark Road. No right turn sign (Rus 012) and no entry (Rus 050) at Old Greenhills Road with new one way entrance.

Map 11 Emerging Preferred Route - Page 37

Greenhills Road, Ballymount Road Upper, Tymon Park PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) CONSIDERATION WILL BE GIVEN TO WIDENING M50 OVERBRIDGE . Queue Relocation Facility before Tymon Park.

Map 12 Emerging Preferred Route - Page 38

Greenhills Road, Ballymount Avenue PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), NEW ROAD LINK CONNECTING GREENHILLS ROAD TO BALLYMOUNT AVENUE, CLOSE GREENHILLS ROAD TO TRAFFIC, NEW PEDESTRIAN LINK TO KEADEEN PARK and new toucan crossing and new vehicle turning area at Greenhills Road.

Map 13 Emerging Preferred Route - Page 39

Ballymount Avenue to Calmount Road at junction EXISTING ROUNDABOUT TO BE CONVERTED TO FULLY SIGNALISED JUNCTION WITH PEDESTRIAN FACILITIES, PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), at Ballymount Avenue.

Map 14 Emerging Preferred Route - Page 40

Calmount Road to Greenhills Road at junction PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION),NEW ROAD LINK CONNECTING CALMOUNT AVENUE TO GREENHILLS ROAD.

Map 15 Emerging Preferred Route - Page 41

Calmount Road, Calmount Avenue at junction EXISTING PRIORITY JUNCTION CONVERTED TO A FULLY SIGNALISED JUNCTION WITH PEDESTRIAN FACILITIES at Calmount Avenue.

Map 16 Emerging Preferred Route - Page 42

Calmount Road continued at junction PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), NEW ROAD LINK CONNECTING GREENHILLS ROAD TO CALMOUNT ROAD, NEW TOUCAN CROSSING and new vehicle turning area.

Map 17 Emerging Preferred Route - Page 43

Greenhills Road at junction PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), ACCESS ARRANGEMENTS TO BE REVISED.

Map 18 Emerging Preferred Route - Page 44

Greenhills Road to Walkinstown Roundabout at junction UPGRADE EXISTING ROUNDABOUT and PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) on Greenhills Road and Walkinstown Road.

Map 19 Emerging Preferred Route - Page 45

Walkinstown Road, Walkinstown Drive and Thomas Moore Road PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), NO RIGHT TURN SIGN (RUS 012) on Walkinstown Road.

Map 20 Emerging Preferred Route - Page 45

Walkinstown Road to Long Mile Road PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), NO RIGHT TURN SIGNS (RUS 012) on Walkinstown Road. Tie into Clondalkin to Drimnagh CBS Proposed Scheme on Long Mile Road.

Map 21 Emerging Preferred Route - Page 46

Walkinstown Road to Long Mile Road, to Drimnagh Road,on Long Mile Road, EXISTING JUNCTION TO BE UPGRADED TO PROVIDE BUS PRIORITY FULLY SIGNALISED WITH PEDESTRIAN FACILITIES, PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION), NO RIGHT TURN SIGNS (RUS 012) on Drimnagh Road. Tie into Clondalkin to Drimnagh CBS Proposed Scheme on Long Mile Road.

Map 22 Emerging Preferred Route - Page 47

Drimnagh Road, Saint Mary's Drive, Errigal Road,on Drimnagh Road, EXISTING ON-STREET PARKING TO BE REMOVED, PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION).

Map 23 Emerging Preferred Route - Page 48

Drimnagh Road, Crumlin Road, Kildare Road,on Crumlin Road at Rafters Road PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) and QUIET CYCLE ROUTE SHARED WITH LOCAL TRAFFIC on Kildare Road.

Map 24 Emerging Preferred Route - Page 49

Crumlin Road, Raphoe Road to Iveagh Gardens and Windmill Road on Crumlin Road PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION).

Map 25 Emerging Preferred Route - Page 50

Crumlin Road, Clonard Road to Brickfield Drive,on Crumlin Road PROPOSED NEW BOUNDARIES (POSSIBLE LAND ACQUISITION)at Guinness Rugby Club, at Clonard Road, Bangor Drive and in front of Crumlin College for Further Education.

Map 26 Emerging Preferred Route - Page 51

Kildare Road to Windmill Road, Cashel Road junction,on Kildare Road REFER TO MAP 41 FOR ALTERNATIVE TRAFFIC ROUTES - KILDARE ROAD, QUIET CYCLE ROUTE SHARED WITH LOCAL TRAFFIC and EXISTING JUNCTION TO BE REALIGNED ROAD WIDENING REQUIREDat Cashel Road junction.

Map 27 Emerging Preferred Route - Page 52

Kildare Road, Clonard Road to Bangor Road,on Clonard Road Roundabout NO ENTRY (RUS 050) EXCEPT BUSES, TAXIS AND BICYCLES, REFER TO MAP 41 FOR ALTERNATIVE TRAFFIC ROUTES - KILDARE ROAD QUIET CYCLE ROUTE SHARED WITH LOCAL TRAFFIC at Cashel Road junction.

Map 28 Emerging Preferred Route - Page 53

Kildare Road, Sail Road, Clogher Road,on Sail Road EXISTING JUNCTION TO BE REALIGNED AND UPGRADED TO FULLY SIGNALISED JUNCTION, QUIET CYCLE ROUTE SHARED WITH LOCAL TRAFFIC and tie into existing schemeat Clogher Road.

Map 29 Emerging Preferred Route - Page 54

Downpatrick Road to Sundrive Road tie into existing schemeat Clogher Road.

Map 30 Emerging Preferred Route - Page 55

Crumlin Road to Sundrive Road, Herberton Road EXISTING JUNCTION TO BE MODIFIED TO PROVIDE IMPROVED ALIGNMENTS AND PEDESTRIAN FACILITIES, PROPOSED NEW BOUNDARIES (POSSIBLE LAND ACQUISITION) Speed limit of 30 on Crumlin Road at junction.

Map 31 Emerging Preferred Route - Page 56

Crumlin Road to Dolphin Road, Grand Canal Speed limit of 30 on Crumlin Road at junction.

Map 32 Emerging Preferred Route - Page 57

Dolphins Barn, South Circular Road, Coombe Hospital NO LEFT TURN SIGNS (RUS 013) at South Circular Road junction. Road widening required at the Coombe Hospital.

Map 33 Emerging Preferred Route - Page 58

Cork Street, Emerald Square, to Marrowbone Lane no change.

Map 34 Emerging Preferred Route - Page 59

Cork Street, Brickfield Lane, to Ormond Street no change.

Map 35 Emerging Preferred Route - Page 60

Cork Street, Ardee Stree to St.Luke's avenue EXISTING JUNCTION TO BE UPGRADED WITH IMPROVED PEDESTRIAN FACILITIES at Ardee Street.

Map 36 Emerging Preferred Route - Page 61

St.Luke's Avenue, to Dean Street and St.Patricks Street Bus Only signal on St.Luke's Avenue, JUNCTION AMENDED TO LEFT OUT ONLY on Francis Street. Road widening required on St. Patricks Street, at St. Patricks close and Bull Alley. Link to proposed scheme Kimmage to City Centre CBC.

Map 37 Emerging Preferred Route - Page 62

Patricks Street to Christchurch Place On Patrick Street EXISTING TRAFFIC LANE CONVERTED TO A NEW BUS LANE and ROAD WIDENING REQUIRED CENTRAL MEDIAN TO BE REMOVED with EXISTING TRAFFIC LANE CONVERTED TO A NEW BUS LANE on Nicholas Street. Road widening required on St. Patricks Street, at St. Patricks close and Bull Alley. Link to proposed scheme Liffey Valley to City Centre CBC.

Map 38 Emerging Preferred Route - Page 60

Bunting Road to Harty Lane and Wallace Road no change.

Map 39 Emerging Preferred Route - Page 61

Bunting Road to Balfe Road, Bunting Road Park no change.

Map 40 Emerging Preferred Route - Page 62

Bunting Road, St.Agnes Road St. Marys Road no change.

Map 41 Alternative Traffic Routes - Page 63

ALTERNATIVE TRAFFIC ROUTES - KILDARE ROAD

LEGEND: THROUGH GENERAL TRAFFIC WILL BE LIMITED ALONG KILDARE ROAD AT THE JUNCTION WITH CLONARD WHERE IT WILL NOT BE PERMITTED TO PASS THE JUNCTION WITH CLONARD ROAD. THE RESTRICTIONS WILL NOT BE APPLIED TO BUSSES CYCLES OR TAXIS.

Green Arrows show that LOCAL WESTBOUND TRAFFIC MAY DIVERT VIA BANGOR ROAD, OLD COUNTY ROAD AND WINDERMILL ROAD.

Blue Arrows show that LOCAL EASTBOUND ACCESS TRAFFIC MAY DIVERT VIA CLONARD ROAD, OLD COUNTY ROAD AND BANGOR ROAD

Red Arrows show that THROUGH GENERAL TRAFFIC MAY DIVERT VIA CRUMLIN ROAD AND SUNDRIVE ROAD.

No access arrows show that NO GENERAL TRAFFIC PERMITTED IN THE DIRECTION INDICATED.